|
THE
government has recently decided to cancel the Japan Bank
for International Cooperation (JBIC) loan for the
Philippine National Oil Company-Energy Development
Corp.’s (PNOC-EDC) Northern Luzon Wind Power Project
Phase 1.
The
P3.51-billion-worth project was originally intended to
supply electricity, power and energy in Ilocos Norte and
consumers in the Luzon grid. The project included the
construction and installation of wind-turbine generators
with a wind farm capacity, a substation and transmission
lines.
In a
letter to the Department of Finance, National Economic
and Development Authority (Neda) deputy director general
Rolando Tungpalan endorsed the request of the PNOC-EDC
for the full cancellation of the JBIC loan for the
project.
“The
requested cancellation is due to the substantial
increase in the project cost [compared with the
appraisal estimates] making the project no longer
viable. The increase in cost was brought about by high
demand for wind-turbine generators worldwide in recent
years and further aggravated by the increase in price of
raw materials for wind-turbine generator manufacturing,
particularly copper and steel,” Tungpalan said in his
letter to Finance Undersecretary Roberto Tan on October
11.
Tungpalan said that no civil works have been started for
the project and no funds have yet been disbursed for the
project.
Neda
documents said the bids received for the wind farm
component exceeded available financing, rendering the
project financially nonviable.
The Neda
Investment Coordination Committee approved a cost of
P2.86 billion for the wind farm in Novermber 2006. This
was the rate used by the PNOC-EDC in negotiating with
the two lowest bidders.
However,
the PNOC-EDC’s efforts were fruitless, since both
bidders were not willing to reduce the contract price in
accordance to PNOC’s levels.
“With
the project rendered non-viable, and compounded by time
constraints with the loan closing on October 24, 2007,
the cancellation of the JBIC loan has become
inevitable,” a Neda document said.
The
project would have a loan maturity of 30 years and a
grace period of 10 years. The interest rate for the wind
farm is at 0.95 percent and another 0.75 percent for
consultancy.
The
signing date for the loan was March 28, 2002, while the
effectivity date was October 24, 2002. The closing date
is October 2007. |