|
THE
National Economic and Development Authority (Neda)
Investment Coordination Committee (ICC) has improved
monitoring of projects funded by official development
assistance (ODA) and now requires all implementing
agencies to submit more detailed information on projects
with cost overruns.
Neda
Deputy Director General Rolando Tungpalan said these
more specific information and data would allow them to
determine how much of the cost overrun can be attributed
to foreign exchange-rate changes, price changes, and
duties and taxes, among others.
To date,
there are 25 ODA projects with cost overruns due to
foreign exchange-rate changes and increases in
right-of-way acquisition costs, labor costs, consultancy
services costs, administrative costs and material costs.
Neda
data show these 25 projects have a total cost overrun of
P30.34 billion. The Department of Public Works and
Highways, long lambasted for inefficiency, not
surprisingly accounts for the bulk of the increase at 42
percent worth P6.69 billion for 13 projects.
The new
requirements were announced after the ICC Cabinet
committee approved the added funding requested by the
Bases Conversion and Development Authority for the
Subic-Clark-Tarlac Expressway Project.
Tungpalan said the Cabinet committee recommended
supplemental funding of P6.48 billion. The original
budget was P26.33 billion. The cost overrun was
attributed to the increase in the price of construction
materials, added Tungpalan.
The
93.77-km, four-lane highway is divided into two major
sections. The first, or the Subic-Clark section, is 50.5
km long; the second, the Clark-Tarlac section, measures
43.27 km.
Three
bridges have to be built—Gumain River Bridge,
Pasig-Potrero River Bridge, and Sacobia-Bamban River
Bridge—and eight interchanges, 35 minor bridges, one
overpass and 36 underpasses.
In
another ICC matter, the investment panel wants to have
additional information from Transco on its effort to
restore power in all of Bicol under the World
Bank-funded Bicol Power Restoration Project.
Tungpalan said the required information has to do with
linked work outside of Bicol that is designed to
increase reliability of the restoration.
The
power restoration will use new steel transmission line
towers along the Naga-Labo, Naga-Tiwi C, BacMan-Daraga,
and Daraga-Naga and Daraga-Tiwi A lines. |