|
AUSTRALIA-based Nido Petroleum Ltd. and its partner
Kairiki Energy Ltd. said they have started site survey
operations in Service Contract 54 (SC54) in northwest
Palawan.
In a
statement, Nido said the site survey is being undertaken
in anticipation of drilling two firm wells with the
WilBoss jack-up rig later this year in the shallow water
area of SC 54.
Nido
said the survey would also cover the deeper water
Gindara prospect, which will be drilled in 2009.
In
total, according to Nido, eight areas will be surveyed
for potential hazards and shallow gas with both analog
and digital grids to evaluate the sea bed and subsurface
at possible drilling locations.
Nido
further noted that an environmental baseline study will
also be conducted as part of its health, safety and
environment focus.
Nido
said the site survey vessel Baruna Jaya has been
contracted through Fugro Survey Pte. Ltd. and the work
is scheduled to take four weeks, depending on weather
conditions.
In May,
Nido completed a share placement to sophisticated
investors generating $41.25 million to finance its
drilling program for SC 54 in northwest Palawan.
Nido
said the share placement was jointly arranged by CLSA
Asia-Pacific Markets and Merrill Lynch, which enabled
them to strengthen and diversify their institutional
shareholder base, including through the introduction of
new funds from London, Singapore and Australia.
“We have
been overwhelmed with the level of interest from
investors who strongly support Nido’s strategy of
accelerating its exploration activities, as shown by the
share placement being well oversubscribed,” Jose Victor
E.A. de Dios, Nido president and chief executive, said
in a statement.
He added
that investors have been excited of learning of the
substantial value afforded by Nido’s exploration
acreage, which represents an opportunity to take part in
what is a unique story in the oil industry today: a
large position in an underexplored hydrocarbon basin
with significant identified oil-in-place potential in
excess of 11 billion barrels (gross, unrisked) across
Nido’s entire exploration portfolio.
With oil
prices climbing to new heights each day, said de Dios,
“this fundraising will enable us, once again, to seize
the first-mover advantage by accelerating our
exploration drilling program.”
Nido
said the funds will be raised through the issue of 82.5
million shares at a price of $0.50 per share. The shares
will be issued within the scope of Nido’s available
share-placement capacity under ASX Listing Rule 7.1.
Settlement of the fundraising was anticipated to occur
on June 2, 2008, with the quotation of the new shares on
June 3, 2008. Upon quotation, Nido’s total issued share
capital will be 1,050,314,774 shares.
On April
29, Nido announced plans to expand its drilling program
in Service Contract 54 from one well to three wells.
Nido and its joint-venture partner Kairiki Energy Ltd.
budgeted to drill at least two shallow-water wells with
a jack-up rig at the end of 2008, followed by drilling
of the Gindara prospect in 2009.
Nido
said the purpose of the fundraising is primarily to
initiate this accelerated three-well drilling program
that will form the beginning of a larger-scale program
to be conducted over the next five years.
Nido
added that the current record oil prices of over A$130
per barrel provide an ideal environment for evaluation
of this area with the aim of rapidly extracting maximum
value from Nido’s Palawan Basin acreage.
Nido
said the funds raised will ensure that Nido is
well-positioned to secure drilling rigs and additional
long lead time items for the increased drilling program
in the current tight market conditions.
In
addition to meeting SC54 drilling commitments, the funds
raised from the share placement will be used to meet
Nido’s working-capital requirements pending the receipt
of Galoc revenues, which have been delayed by
approximately 60 days, resulting in increased capital
costs from initial budgetary amounts.
Nido is
confident that, with hook-up and commissioning of the
floating production storage and offloadig under way,
further delays to the Galoc project are unlikely to
arise, with first oil supposed to be expected in June. |