HOME PAGE ABOUT US CONTACT US SUBSCRIBE ADVERTISE ARCHIVES
TOP STORIES NATION ECONOMY COMPANIES SHIPPING OPINION PERSPECTIVE LIFE SPORTS BANKING
SEARCH ENGINE
WWWOur Site
Anchored by Jonathan dela Cruz, Salvador Escudero, Boying Remulla, Teddy Boy Locsin and Alvin Capino
Monday to Friday
8:00pm-10:00pm

ARTICLE SERVICES
  • bookmark this page
  • print this article
  • view archive
  • Araneta mall told to pay P114M
     
    By Joel San Juan
    Reporter

    THE Court of Appeals (CA) has directed property developer Araneta Center Inc. to pay a construction company the amount of P114 million, representing its unpaid billings for the construction of the Gateway Mall in Cubao, Quezon City.

    In a 75-page decision penned by Associate Justice Agustin Dizon, the CA’s Sixteenth Division modified the December 28, 2006, decision of the Construction Industry Arbitration Commission (Ciac) awarding the amount of P231.3 million to CE Construction Corp. (Cecon).

    The appellate court, likewise, required Cecon to compensate Araneta in the amount of P31.56 million, representing liquidated damages, defective and incomplete works and permits, licenses and other advances.

    Araneta and Cecon have been doing business together for more than 25 years.

    Based on the records, Araneta started conceiving a redevelopment plan for the Araneta Center Complex. In June 2002 Araneta formalized the project and sent invitations to different construction companies inviting them to bid on the project.

    Cecon was among the contractors invited by Araneta to participate in the bidding for the project. On August 30, 2002, Araneta formally accepted Cecon’s offer to do the project in the amount of P1.54 billion.

    Araneta subsequently released to Cecon the down payment of P200 million.

    The contract period for the project was for 400 calendar days with a completion date of January 9, 2004. The project was not completed in the original time allotted and Cecon submitted several requests for time extensions.

     Araneta informed Cecon that, as a cost-saving measure, Araneta would be personally purchasing certain equipment and materials, such as elevators, escalators, chillers, generator sets, indoor substation, cooling towers as well as pumps and tanks, for the project and the amounts would be taken out of Cecon’s contract.

    Araneta deducted a total of P251.4 million representing the value or costs or both of the items deleted or taken out from Cecon’s scope of work.
    As of
    May 30, 2005, Araneta had a balance of P1.186 billion for Cecon’s supply and installation of the subject equipment. Araneta claims that it was unable to settle this balance because Cecon did not furnish Araneta with copies of the purchase orders-sales invoices for certain equipment it supplied and installed.

    Following delays, Cecon claimed that Araneta’s refusal to pay Cecon the amounts due it as billed, was affecting its ability to continue the project.

    While the last undisputed completion date before the commencement of the arbitration before the Ciac was March 15, 2004, Cecon’s percentage of completion of the project was only 81.92 percent as of April 5, 2004.

    On June 30, 2004, Araneta reminded Cecon that the 400 day completion date had long since passed and that it was reserving all its rights arising from such lapse.

    Despite the uncompleted state of the Gateway Mall, Araneta also allowed its tenants to come in on August 2004.

    Araneta also proceeded with its scheduled soft blessing of the mall on November 26, 2004.

    Araneta notified Cecon about a number of non-conforming or defective works or both including, among others, the unevenness of the exterior walls of the mall, leaks in the cistern tanks and leaks in the exterior walls.

    Concurring with the ruling were Associate Justices Regalado Maambong and Celia Librea-Leagogo.

    OTHER STORIES

    JG offers to buy Petron stake


    Pressure on rates rises; BSP ‘neutral’


    Crude oil trades near $122 a barrel


    7 of 10 Pinoys find it hard to buy basic needs


    Rice climbs 4th day after Burma cyclone


    GIR rises to $36.7B in first four months


    RP to tap budget aid offered by ADB


    RP to send medical team to Burma


    CHED chief sees 10% tuition hike


    Araneta mall told to pay P114M


    ’07 a banner year for mutual funds