HOME PAGE ABOUT US CONTACT US SUBSCRIBE ADVERTISE ARCHIVES
TOP STORIES NATION ECONOMY COMPANIES SHIPPING OPINION PERSPECTIVE LIFE SPORTS BANKING
SEARCH ENGINE
WWWOur Site
Anchored by Jonathan dela Cruz, Salvador Escudero, Boying Remulla, Teddy Boy Locsin and Alvin Capino
Monday to Friday
8:00pm-10:00pm

ARTICLE SERVICES
  • bookmark this page
  • print this article
  • view archive
  • Hanjin loses P.3-B case to subcontractor
    By Joel R. San Juan
    Reporter

    SOUTH Korean construction giant Hanjin Heavy Industries and Construction Co. Ltd. has lost a P300-million case to a former subcontractor that it accused of abandonment, with the Supreme Court (SC) giving more weight to the subcontractor’s right to be paid for a completed stage of construction at the Davao International Airport.

    The SC ordered the construction firm to pay its local subcontractor Dynamic Planners and Construction Corp. (DPCC) P300 million and the interest demanded by the latter for the construction of the Davao International Airport, now known as the Francisco Bangoy International Airport.

    Associate Justice Presbitero Velasco Jr. of the Court’s Second Division, in ruling thus, has affirmed with modification the August 31, 2005, decision of the Court of Appeals ordering Hanjin to pay PDCC P293.95 million plus retention money of P58.2 million.

    However, the SC reduced from 12 percent to 6 percent the annual interest on the retention money, reckoned from November 20, 2003, until the total award becomes final and executory.

    A yearly interest of 12 percent on the total amount adjudged by the Construction Industry Arbitration Commission (CIAC), as affirmed by the CA with modifications, shall likewise be imposed against Hanjin starting from the CIAC’s issuance of the final award on September 2004 until full payment of the award.

    The Court dismissed the claim of Hanjin that DPCC was not entitled to the retention money and should instead be held liable for damages for abandoning the project.

    DPCC replied it never abandoned the project but merely suspended it due to Hanjin’s failure to release the down payment and the payment of its progress billing as agreed upon.

    DPCC further told the Court that when project works had reached 94-percent completion in December 2002, Hanjin took over the project for alleged abandonment.

    “Instead of paying, Hanjin held on to Dynamic’s retention money. Worse still, Hanjin willfully and in apparent bad faith took over the unfinished work of Dynamic. To us, and to CIAC and the CA earlier, Hanjin in effect waived any and all of its rights to hold Dynamic liable for any defects, deficiencies, or unfinished work,” said the SC decision.

    DPCC accused Hanjin of ignoring flaws in the designs of the project despite notification from experts; the flaws later resulted in cracks appearing in the passenger-terminal beams. Hanjin blamed the DPCC for the defects, but the Association of Structural Engineers of the Philippines-Task Force Davao International Airport cleared the DPCC, having failed to discover evidence that the subcontractor deviated from the design plans and specifications.

    The Davao airport contract was earlier awarded by the Department of Transportation and Communications to Hanjin, who bid P1.0 billion, 65 percent of which was payable in pesos and the remaining 35 percent in US dollars.

    OTHER STORIES

    8.3% inflation way past April forecast


    Oil trades near $120 on high demand


    Relief from high power rates?


    Government-to-government rice buy, sans bidding, eyed


    Cyclone may force Burma to import rice


    Hanjin loses P.3-B case to subcontractor


    Meralco stocks take a hit from shareholders’ row


    Government must pay Davao landowners P1B


    Labor frowns on employers’ Ecola offer


    RP pearls wow ’em at Basel expo


    US investment firm in Medical City